+41 27 948 08 60
info@pixon-ch.com
3 locations

Sterile Fill & Finish

No items found.

Project type
General planner

Client
Client confidential 

Investment sum
CHF 20 million

Planning / execution time
2014 - 2018

Project description
A new Fill & Finish system was installed on a production area of 1,000 m2. pixon was responsible for the planning and realization of the system and the necessary structural and building technology measures.

Activities:‍

  • Specialist coordination HVACS
  • 3D management
  • Collision check
  • HVAC planning (ventilation, cold and hot water, HPW, clean steam, waste water, drinking water, nitrogen (cleanroom-compatible), instrument air, process air (cleanroom-compatible))
  • Specialist fire protection planning
  • Creation of maintenance concept
  • Maintenance support
  • Creation of specification sheets for systems, media and rooms
  • Procurement of equipment and suppliers
  • Construction site coordination
  • Commissioning
  • Qualification of all GMP-relevant systems

Project Challenge
The planning and implementation had to meet the pharmaceutical requirements for a sterile fill & finish within a very short time frame. The increased requirements were verified by a swissmedic inspection.